AKKİM EPOXY PLANT

Turnkey construction of the plant consisting of Epoxy Production and Storage Buildings, Cooling Tower, HCL, MCC – Transformer, Hot Oil, Air Nitrogen Production Buildings, Tank Areas, Pure Water Plant, Fire Water Storage Tank and Pump Rooms, with a total covered area of 27,570 m² within Yalova Yalkim OSB.

EMPLOYER

Akkim Kimya Sanayi ve Tic. A.Ş. // akkim.com.tr

PROJECT DETAILS

  • Project Name: Akkim Epoxy Plant
  • Project Location: Yalova Yalkim OSB (Yalova Composite and Chemistry Specialized Organized Industrial Zone)
  • Project Type: Industrial
  • Project Duration: 24 months
  • Project Area: 104,832 m²
  • Project Construction Area:
    • Epoxy Plant Buildings: 21,462.22 m²
    • Storage (750 EPR): 1,652.72 m²
    • HCL Building: 243.29 m²
    • MCC Transformer Buildings: 1,064.09 m²
    • Hot Oil Unit Building: 145.47 m²
    • Air Nitrogen Buildings: 581.68 m²
    • Tank Areas: 1,913.14 m²
    • Pure Water Plant: 146.64 m²
    • Fire Water Storage Tank and Pump Room: 360.24 m²
  • Project Construction System: Reinforced Concrete-Steel

SERVICES

Design and Construction EPC